          Managing risks in research
          ==========================
       
          Research is uncertain. It’s not clear what problems you will hit. It’s
          not clear how many problems you will hit. It’s not clear how long
          success will take or what success will look like or whether you will
          even succeed. When we talk about research, we often focus on the
          ideas, the sudden insight, the stroke of genius, standing on the
          shoulders of giants, etc. We sometimes talk about uncertainty and
          persistence. But we very rarely talk about risk and, most importantly,
          how to manage it.
       
          And it’s not just that risk is an unfortunate side-effect of tackling
          hard, unsolved problems; dealing with risk is our job. In 15+ years of
          industrial research, I’ve come to believe that
       
            An essential part of the job of an industrial researcher is to
            keep unacceptable levels/types of risks away from production
            engineering teams so that they can execute as efficiently as
            possible without too many false steps.
       
          Managing risk is also a key part of a company’s research strategy:
          tracking long-term trends for risks (and opportunities) for the
          business; maintaining a balance of high-risk and low-risk projects;
          balancing short-term projects with the more risky long-term projects;
          etc. But, for this post, I’ll focus on managing risks in individual
          projects.
       
          I have a little list
       
          The first part to managing the risks in a research project is to make
          a list of all the risks you can think of.
       
            * 
       
              There’s usually a bunch of technical questions: a list of
              challenges you need to solve. These are usually fairly obvious
              because you already know that the existing approach doesn’t work.
       
            * 
       
              Then there’s questions about how well your solution will work:
              Will it be 80% effective? 90%? 99%? Will it be fast enough? small
              enough? etc.
       
            * 
       
              But then we get into the really big risks: Are we solving the
              right problem? Did we understand the issue? Did the problem really
              need to be solved? As we navigated the twists and turns of finding
              a solution, did we lose track of the problem? Has the problem
              changed during the course of the project?
       
            * 
       
              Another important risk to consider is whether you need to do
              anything at all? Maybe somebody has already solved the problem. In
              industrial research, this is great news because it means that you
              can solve the problem quickly and move onto the next problem.
              (There is no shortage of hard problems in industry.) In practice
              though, this rarely happens because the problems we hit in
              industry always have unsolved corners to them and, until you have
              solved all the problems, it is not ready for production
              engineering teams to implement. (Some of my favourite research
              papers are about all the surprising issues that are encountered in
              solving a problem.)
       
          For [4]my current project, I have a [5]list of around 50 risks that
          I’m worried about.
       
          Once you have a list of risks, you need to estimate the size of each
          risk: how much impact it could have and how uncertain you are about
          whether it is a real problem. This is basically impossible to do at
          the start of a project: you just don’t understand enough to list all
          the risks and rank them accurately. This is an iterative process so
          just start with a coarse-grained ranking system like high, medium and
          low and do the best you can.
       
          Managing your risk budget
       
          Now the hard part… try to kill your project.1 Pick the largest risk
          and try to show that it is so big that your project is bound to fail.
          Be creative. Try really hard to kill it. This is a bit brutal but it’s
          a lot better to find a problem yourself early in a project than to
          have somebody else find the problem later.
       
          [[6]Laurence Tratt (King’s College London) [7]wrote about how he has
          applied a similar approach at several points in his career.]
       
            If it’s your job to eat a frog, it’s best to do it first thing in
            the morning. And If it’s your job to eat two frogs, it’s best to
            eat the biggest one first.
       
            — Mark Twain
       
          Keep going with any risks that you think could potentially doom your
          project to failure.
       
          Along the way, you will probably find that you need to change your
          plans to avoid some risk. For example, if you become uncertain that
          you can automate 100% of a problem: you might change your plan to
          allow some small amount of human assistance. And then you would amend
          the risk to include questions about whether you are able to automate
          enough of the problem to be useful and whether your users can
          realistically solve the part that you leave for them.
       
          And, as you work the problem, you will probably realize that you
          misunderstood the problem, that you had left out some risks, etc. This
          is good: you are building a clearer understanding of the problem;
          building a better project plan; and saving production teams from risk.
       
          As you work on each risk, your goal is not to reduce that risk to
          zero. Your goal is just to reduce the size of the biggest risk by
          solving part of the problem and/or making your assessment of the risk
          more accurate. Especially at the start of a project, you have lots of
          risks to assess so it is best to take a brief look at all the big ones
          early and revisit them later. Another way of looking at this is that,
          in the early stages, you will explore the topic in a breadth-first
          manner where you understand the topic and the risks; and, in later
          stages, you will shift more to a depth-first approach where you work
          more efficiently by diving deep and maintaining focus on each aspect
          for longer.
       
          You can only manage so much of this per month: it is psychologically
          hard to kill your own ideas; you need to build part of the system
          before you have enough to attack; and you have to make forward
          progress. So, give yourself a risk budget: a certain number of days
          per month that you will spend trying to reduce risk.
       
          On my [4]current project, I manage the risk budget by doing “risk
          sprints” that are limited to a maximum of one week. In that week, I
          try to move as quickly as possible. I take good notes about what I do
          and what I learn but I allow myself to ignore every software
          engineering rule in the book. My job during that week is just to learn
          as much as I can about the risk so that I can update the risk
          assessment. Along the way though, I am hoping to learn something
          useful to move the project forward. So, at the end of the week, I
          switch to software engineering mode: turning any useful ideas into
          decent quality code or writing design documents for later. And, since
          the project is all open source, sometimes I write blog post about
          things like [8]profiling or fixing [9]bottlenecks found by profiling.
       
          And every few months, I go back to the list of risks and update my
          sense of which risks matter most and think about the risks I should
          work on over the next few months, whether there are any logical
          order/dependencies between them and what I need to build to support
          that.
       
          Summary
       
            * 
       
              An essential function of industrial research is to keep
              unacceptable levels and types of risk away from production
              engineering teams.
       
            * 
       
              We can manage that risk by
       
                * 
       
                  making a very long list of all the risks we can think of
       
                * 
       
                  guessing the size of each risk
       
                * 
       
                  tackling the biggest risks first
       
                * 
       
                  updating the list of risks and our guesses about size
                  throughout the life of the project.
       
            * 
       
              With luck, the number of high-rated risks will go down over time.
              If not, you should seriously consider killing your project.
       
          In closing… the idea here is not to fixate on risk: running around
          shouting that the sky is falling down. Instead, it is like the [10]Getting
          Things Done productivity system: by writing down all the risks, you
          can stop worrying about them because you know that you have that taken
          care of and you have a plan to handle them. Which lets you focus on
          other aspects of the project. The tweak that I am adding is the idea
          that you can use the list of risks to help decide what part of the
          problem to work on next.
       
          ---------------------------------------------------------------------
       
            1. 
       
              From comments on Twitter, I realize that I did not make it clear
              that the approach in this article is mostly for multiperson,
              multiyear projects. For a student project, the PhD supervisor
              would be thinking of some of these issues before suggesting the
              project to avoid the student discovering the fatal flaws for
              themselves some distance into the project. ↩
       
          Written on August 6, 2021.
          The opinions expressed are my own views and not my employer's. [11]
          [12] [13] [14] [15] [16]
       
          1. https://alastairreid.github.io/
          2. https://alastairreid.github.io/about/
          3. https://alastairreid.github.io/papers/
          4. https://project-oak.github.io/rust-verification-tools/
          5. https://project-oak.github.io/rust-verification-tools/2021/08/15/rvt-risks.html
          6. https://tratt.net/laurie/
          7. https://tratt.net/laurie/blog/entries/stick_or_twist.html
          8. https://project-oak.github.io/rust-verification-tools/2021/03/12/profiling-rust.html
          9. https://project-oak.github.io/rust-verification-tools/2021/05/19/fixing-bottlenecks.html
          10. https://gettingthingsdone.com/
          11. mailto:alastair.d.reid@gmail.com
          12. https://github.com/alastairreid
          13. https://www.linkedin.com/in/alastairdreid
          14. https://alastairreid.github.io/feed.xml
          15. https://www.twitter.com/alastair_d_reid
          16. https://orcid.org/0000-0003-4695-6668